Tianjiang Big Data Center UPS Project: Modular Case Drives PUE 1.25 Green Transition

Ⅰ. Project Overview

  1. Base Planning
    • Tianjiang Tianjin Base plans 8 green data centers, covering 339,000㎡, with capacity for 40,000 6kW standard cabinets.
    • Scheduled to become a key data center hub in the Beijing-Tianjin-Hebei region. The No.1 data center leads the initiative.
    • Tianjiang Technology prioritizes high-efficiency solutions to drive green data center development.
Tianjiang Big Data Center UPS Project: Modular Case Drives PUE 1.25 Green Transition
Tianjiang Big Data Center UPS Project: Modular Case Drives PUE 1.25 Green Transition

Ⅱ. Core Challenges

  1. Energy Efficiency Optimization
    • Goal: Reduce data center PUE below 1.25 to maximize energy utilization.
  2. Cost Control
    • Requirement: Lower total cost of ownership (TCO) for construction and operations.
  3. Green Transition
    • Align with China’s “Double Carbon” strategy to achieve data center carbon neutrality.

Ⅲ. Solutions

  1. Modular UPS Deployment
    • BKPOWER provides modular UPS systems, meeting demands for reliability, high efficiency, and energy savings.
    • Compact design minimizes floor space, suitable for high-density data center setups.
  2. Energy Savings Impact
    • PUE reduced below 1.25, saving ~4.8 million kWh/year and cutting CO₂ emissions by ~4,500 tons.
Technical AdvantagesSpecific Performance
Modular designOn-demand expansion, lower CAPEX
High-efficiency conversion96% system efficiency, reduced energy loss
Green energy solutionAligns with carbon reduction goals

Ⅳ. Project Achievements

  1. High-Efficiency Operation
    • UPS automatically switches modes based on input power, achieving 96% overall efficiency.
  2. Intelligent Energy Saving
    • Enables module hibernation during low loads to minimize energy waste.
  3. Security Management
    • Open data interfaces allow real-time monitoring of power cabinet metrics, paired with battery BMS for dual-layer safety assurance.